Southend

Sector

Education

​

Client

Ashe Construction Ltd

​

Project Manager

Orbell Associates

​

Architect

Designcubed

Value

£720K

​

Form of Contract

JCT 2016

​

Completion Date

September 2018

​

Duration

26 Weeks

Location

The standalone two storey building comprised of a new first floor dining facilities, catering kitchen, 10 classrooms and associated communal and toilet facilities.

​

Gas fired boilers were installed along with Air Handling Units to heat the building.

​

Mitsubishi’s GUG Units were used in the classrooms in one of the countries first projects to use the new “Lossnay Air Processing DX Units” to provide both ventilation along with heating and cooling.

​

A full BMS system was installed to control the buildings mechanical services. 